For this project, our company was responsible for delivering and installing heating, water supply, sewage and cooling systems for hotel – Flemingsbergdalen.
Our contract part of this project took 12 months from the start till end.
For heating we have used total of 4 heat exchangers. Two of them are used for preparing hot domestic water (2 x 376 kW), another one has 545 kW of power and is mainly used for heating system. The last heat exchanger is used for cooling system and has 206 kW of total power. It has a heating power plant in the basement. Enso Projects was also responsible for water supply system pipelines.
Sewage system includes cast iron pipes. This is used for soundproofing capabilities.